NOrth Cameron St Drainage improvements

FY 2024 ANNUAL BUDGET

SUMMARY

PROJECT TITLE: North Cameron St Drainage Improvements

DEPARTMENT: Public Services

BUDGET CODE: 312-4121-441.83-04

JUSTIFICATION: Improves existing service

START DATE (FY): 2018

END DATE (FY): 2024

PROJECT DESCRIPTION:

The project would consist of making drainage piping improvements and constructing storm water management ponds to help alleviate the flooding that occurs on N. Cameron Street during large rain events.

RELATIONSHIP TO STRATEGIC PLAN:

Goal 2 - Establish the foundations for a vibrant community by stimulating development of affordable housing, revitalizing catalyst sites, and building smart infrastructure.

PROJECT OBJECTIVES / STATUS:

The existing storm drainage infrastructure on N. Cameron is too small and during heavy rain events there is extensive street flooding. This project will help alleviate that flooding.

Cost Estimate

Funding Sources


Note: Reference period 2022-23 includes all prior years and 2028-29 includes all future years.

OPERATING IMPACTS

The estimated annual operating impact is projected to be $500,000 in debt service and $20,000 in storm water maintenance costs.