Department of Public Works

General Capital Projects

Spending on Public Works General Capital Projects

Status of Active General Capital Projects as of September 30, 2023

The Department of Public Works has undertaken the following capital projects to improve and maintain the City's infrastructure, which may include streets, sidewalks, traffic systems, and public buildings. The status of these capital projects is provided by Public Works to the Capital Review Committee on a quarterly basis. This page will therefore be updated at the end of every quarter with information received at the Capital Review Committee meeting.


The Life Budget amount listed below indicates the total amount of money budgeted over the entire life of the project. The FY 2024 Budget amount indicates the amount of money available to spend in FY 2024. Any remaining funds left over at the end of the fiscal year will be carried over into FY 2025 and will become the FY 2025 Budget.

Note: The below numbers are as of September 30, 2023, the end of the first quarter of FY 2024.

22032 - Street Paving & Reconstruction

This project was approved as part of the FY 2022 Annual Budget and provides funds for routine street paving and reconstruction of deteriorated roadways throughout the City based on condition and use, in order to maintain roadway network infrastructure.


Life Budget: $2,000,000

Life Actual Expenditure: $611,574

FY 2024 Budget: $1,907,135

FY 2024 Actual Expenditure: $518,709


Expected Completion Date: July 31, 2024

20033 - Emergency Sidewalk Repairs

This project was approved as part of the FY 2020 Annual Budget and provides funds for emergency repairs to damaged sidewalks throughout the City.


Life Budget: $500,000

Life Actual Expenditure: $260,809

FY 2024 Budget: $396,614

FY 2024 Actual Expenditure: $157,423


Expected Completion Date: July 31, 2024

20038 - Traffic System Infrastructure

This project was approved as part of the FY 2020 Annual Budget and provides funds for the implementation of the Improved Readability of Street Name Signs program; for traffic infrastructure improvements including traffic signals, smart parking meters and decorative street lights; and for implementing additional emerging parking technologies, in order to maintain the existing traffic control system.


Life Budget: $2,000,000

Life Actual Expenditure: $379,730

FY 2024 Budget: $2,000,000

FY 2024 Actual Expenditure: $379,730


Expected Completion Date: December 31, 2024

20032 - Street Paving & Reconstruction

This project was approved as part of the FY 2020 Annual Budget and provides funds for routine street paving and reconstruction of deteriorated roadways throughout the City based on condition and use, in order to maintain roadway network infrastructure.


Life Budget: $7,000,000

Life Actual Expenditure: $6,973,893

FY 2024 Budget: $36,106

FY 2024 Actual Expenditure: $10,000


Expected Completion Date: July 1, 2024

18032 - Street Paving & Reconstruction

This project was approved as part of the FY 2018 Annual Budget and provides funds for routine street paving and reconstruction of deteriorated roadways throughout the City based on condition and use, in order to maintain roadway network infrastructure.


Life Budget: $5,000,000

Life Actual Expenditure: $4,974,774

FY 2024 Budget: $27,197

FY 2024 Actual Expenditure: $1,971


Expected Completion Date: December 31, 2023

18039 - Wilmington Transportation Initiatives

This project was approved as part of the FY 2018 Annual Budget. Funds were used to match DelDOT funding for WILMAPCO Projects and ADA curb ramps.


Life Budget: $2,294,883

Life Actual Expenditures: $2,294,883

FY 2024 Budget: $0

FY 2024 Actual Expenditures: $0


Expected completion date: Complete

18038 - Traffic System Infrastructure

This project was approved as part of the FY 2018 Annual Budget. Funds will be used for infrastructure improvements in conjunction with the I-95 viaduct maintenance.


Life Budget: $1,000,000

Life Actual Expenditures: $108,049

FY 2024 Budget: $967,000

FY 2024 Actual Expenditures: $65,630


Expected completion date: December 31, 2024

18035 - Building Improvements

This project was approved as part of the FY 2018 Annual Budget. Funds will be used for HVAC and perimeter heating improvements to the Louis L. Redding City/County Building.


Life Budget: $1,000,000

Life Actual Expenditures: $778,248

FY 2024 Budget: $345,566

FY 2024 Actual Expenditures: $123,814


Expected completion date: July 31, 2024

18033 - Emergency Sidewalk Repairs

This project was approved as part of the FY 2018 Annual Budget for emergency repairs to damaged sidewalks, as identified by Licenses & Inspections and managed by the Department of Public Works.


Life Budget: $700,000

Life Actual Expenditures: $700,000

FY 2024 Budget: $0

FY 2024 Actual Expenditures: $0


Expected completion date: Complete

18028 - Turner Building Carpet Replacement

This project was approved as part of the FY 2018 Annual Budget for the replacement of worn carpeting in the William G. Turner Building. Remaining funds may be reprogrammed.


Life Budget: $95,000

Life Actual Expenditures: $94,187

FY 2024 Budget: $813

FY 2024 Actual Expenditures: $0


Expected completion date: Complete

16050 - City/County Building

Louis L. Redding City/County Building

This project was approved as part of the FY 2016 Annual Budget. Funds will be used for various renovations to the Louis L. Redding City/County Building, including new flooring and lighting for the lobby.


Life Budget: $800,000

Life Actual Expenditures: $789,909

FY 2024 Budget: $10,091

FY 2024 Actual Expenditures: $0


Expected completion date: December 31, 2023

16051 - Gas Monitoring & Ventilation

This project was approved as part of the FY 2016 Annual Budget and included installation of carbon monoxide monitors at the Turner Municipal Complex. Remaining funds may be reprogrammed.


Life Budget: $200,000

Life Actual Expenditure: $197,034

FY 2024 Budget: $12,054

FY 2024 Actual Expenditure: $9,088


Expected completion date: Complete

16040 - South Wilmington Transportation Improvements

This project was approved as part of the FY 2016 Annual Budget. Funds were used for transportation improvements in South Wilmington.


Life Budget: $1,000,000

Life Actual Expenditure: $1,000,000

FY 2024 Budget: $0

FY 2024 Actual Expenditure: $0


Expected completion date: Complete

16039 - Transportation Initiatives

This project was approved as part of the FY 2016 Annual Budget. Funds will be used in conjunction with matching DelDOT funding for WILMAPCO projects and ADA-compliant curb ramps.


Life Budget: $1,500,000

Life Actual Expenditure: $1,476,565

FY 2024 Budget: $23,435

FY 2024 Actual Expenditure: $0


Expected completion date: December 31, 2023

16038 - Traffic System Infrastructure

This project was approved as part of the FY 2016 Annual Budget. Funds will be used for infrastructure improvements in conjunction with the I-95 viaduct maintenance.


Life Budget: $550,000

Life Actual Expenditure: $548,622

FY 2024 Budget: $1,790

FY 2024 Actual Expenditure: $412


Expected completion date: December 31, 2023

16035 - Building Improvements

This project was approved as part of the FY 2016 Annual Budget. Funds were used for ongoing improvements and maintenance to the elevators and HVAC system in the Louis L. Redding City/County building.


Life Budget: $2,000,000

Life Actual Expenditure: $2,000,000

FY 2024 Budget: $0

FY 2024 Actual Expenditure: $0


Expected completion date: Complete

16033 - Emergency Sidewalk Repairs

This project was approved as part of the FY 2016 Annual Budget. Funds were used for emergency repairs to damaged sidewalks as identified by the Department of Licenses & Inspections.


Life Budget: $700,000

Life Actual Expenditure: $700,000

FY 2024 Budget: $0.00

FY 2024 Actual Expenditure: $0.00


Expected completion date: Complete

16032 - Street Paving & Reconstruction

This project was approved as part of the FY 2016 Annual Budget. Funds were expended for routine street paving and the reconstruction and maintenance of deteriorated roadways throughout the City based on the condition and use, in order to maintain roadway network infrastructure.


Life Budget: $6,000,000

Life Actual Expenditure: $6,000,000

FY 2024 Budget: $0

FY 2024 Actual Expenditure: $0


Expected completion date: Complete

14039 - Transportation Initiatives

This project was approved as part of the FY 2014 Annual Budget and provides local matching funding for WILMAPCO TIP, Transportation Enhancement, and legislator-sponsored projects, as well as citywide lighting improvements and the installation of pedestrian ADA curb ramps. Funds are being used to change out one-third of the Delmarva Street lights to LED.


Life Budget: $4,300,000

Life Actual Expenditure: $4,273,860

FY 2024 Budget: $62,551

FY 2024 Actual Expenditure: $36,411


Expected completion date: June 30, 2024

14038 - Traffic System Infrastructure

This project was approved as part of the FY 2014 Annual Budget. Funds were used for an ongoing traffic signal improvement program, which involves upgrading both vehicular and pedestrian traffic signals and associated infrastructure to meet ADA standards.


Life Budget: $550,000

Life Actual Expenditure: $550,000

FY 2024 Budget: $0

FY 2024 Actual Expenditure: $0


Expected completion date: Complete

14035 - Building Improvements

This project was approved as part of the FY 2014 Annual Budget. Funds were used for ongoing improvements and maintenance to the elevators and HVAC system in the Louis L. Redding City/County building.


Life Budget: $2,000,000

Life Actual Expenditure: $2,000,000

FY 2024 Budget: $0

FY 2024 Actual Expenditure: $0


Expected completion date: Complete

12034 - Transportation Initiatives

This project was approved as part of the FY 2012 Annual Budget and provided local matching funding for WILMAPCO TIP, Transportation Enhancement, and legislator-sponsored projects, as well as citywide lighting improvements and the installation of pedestrian ADA curb ramps.


Life Budget: $2,250,000

Life Actual Expenditure: $2,250,000

FY 2024 Budget: $0

FY 2024 Actual Expenditure: $0


Expected completion date: Complete

06527 - Signal Improvements

This project was approved as part of the FY 2006 Annual Budget. Funds were used for various pedestrian improvements, including those on Concord Avenue and Walnut Street.


Life Budget: $4,000,000

Life Actual Expenditures: $4,000,000

FY 2024 Budget: $0

FY 2024 Actual Expenditures: $0


Expected completion date: Complete