Storage, Automation & Modernization
FY26 Capital Budget
SUMMARY
PROJECT TITLE: Storage, Automation & Modernization
DEPARTMENT: Electric and Gas Utility
FUNDING SOURCE (FUND): Electric RR&I (401)
PROJECT TYPE: Non-Recurring
START DATE: 10/1/2025
END DATE: 9/30/2026
*Funding and timeline are subject to change.
PROJECT DESCRIPTION
| The project enables the installation and operation of the utility's first large-scale battery energy storage system (BESS) along with several critical grid hardening enhancements. Primary goals of this project include improving grid resilience and operational flexibility while lowering the utility's carbon footprint, that can be replicated elsewhere on the City's electric grid. |
STRATEGIC PLAN OBJECTIVE
Public Infrastructure - OBJECTIVE 4-1: Be a Leader in Utility Service Delivery