Storage, Automation & Modernization

FY26 Capital Budget

SUMMARY

PROJECT TITLE: Storage, Automation & Modernization

DEPARTMENT: Electric and Gas Utility

FUNDING SOURCE (FUND): Electric RR&I (401)

PROJECT TYPE: Non-Recurring

START DATE: 10/1/2025

END DATE: 9/30/2026

 

*Funding and timeline are subject to change.

PROJECT DESCRIPTION

The project enables the installation and operation of the utility's first large-scale battery energy storage system (BESS) along with several critical grid hardening enhancements. Primary goals of this project include improving grid resilience and operational flexibility while lowering the utility's carbon footprint, that can be replicated elsewhere on the City's electric grid. 

STRATEGIC PLAN OBJECTIVE

Public Infrastructure - OBJECTIVE 4-1Be a Leader in Utility Service Delivery