Terminal Passenger Loading Bridge Replacement

FY26 Capital Budget

SUMMARY

PROJECT TITLE: Terminal Passenger Loading Bridge Replacement - A5/A6

DEPARTMENT: Aviation

FUNDING SOURCE (FUND): Passenger Facility Charge 

PROJECT TYPE: Non-Recurring

START DATE: 10/1/2025

END DATE: 9/30/2026

 

*Funding and timeline are subject to change.

PROJECT DESCRIPTION

Project includes the design, engineering, permitting, construction, construction administration, and resident project representatives for the purposes of procurement and installation of two (2) new passenger loading bridges for gates A5 and A6.  The bridges will be equipped with self-contained air condition units, preconditioned air (PCA) units, ground power units (GPUs) and potable water connections. 

STRATEGIC PLAN OBJECTIVE

ECONOMIC DEVELOPMENT - OBJECTIVE 1-3Increase Tallahassee International Airport's economic impact on the region