New Police Facility
FY26 Capital Budget
SUMMARY
PROJECT TITLE: New Police Facility
DEPARTMENT: Tallahassee Police Department
FUNDING SOURCE (FUND): Future Capital Bond Series, Capital Bond Series 2024, Capital Bond Series 2025
ESTIMATED COST: $138,000,000
PROJECT TYPE: Non-recurring
APPROPIATED FUNDS THROUGH FY26: $138,000,000
START DATE: 4/10/2017
CONSTRUCTION END DATE: Winter 2026
*Funding and timelines are subject to change.
PROJECT DESCRIPTION
Due to the building’s age and scope of daily use, the current Tallahassee Police Department (TPD) facility is in need of significant repair and updating. Additional space is also necessary for evidence storage, public and employee parking, and anticipated growth. There is very limited parking and meeting space, which hinders on-site interaction between TPD and the community. Current staffing levels occupy existing space with little opportunity for expansion and portable buildings that have been utilized as a stop gap storage measure are beginning to fail.
In 2020, the City Commission unanimously approved the construction of a new Tallahassee Police Department Headquarters facility at the former Northwood Mall site. The former mall complex has since been demolished and the project has completed the infrastructure phase which includes the installation of all underground utilities, a new stormwater pond, roads, lighting, sidewalks, and landscaping. Design and competitive bidding are complete and subcontracts are being awarded by the competitively selected construction manager. The City’s Department of Building Construction is responsible for project management and oversight.
STRATEGIC PLAN OBJECTIVES
PUBLIC SAFETY - OBJECTIVE 5-4: Provide state of the art technology and facilities to support public safety initiatives.