WATER MAIN IMPROVEMENT - BURLINGTON AVENUE
VILLAGE OF LISLE | FISCAL YEAR 2023/2024 BUDGET
SUMMARY
PROJECT TITLE: Water Main Improvement - Burlington Avenue
DEPARTMENT: Public Works
START DATE (FY): 05/01/2023
END DATE (FY): 04/30/2025
PROJECT DESCRIPTION
As part of the Burlington Avenue Reconstruction Project, the Village plans to replace approximately 3,000 lineal feet of 8” diameter water main and line approximately 400 lineal feet of 8” diameter water main. The portion of the water main scheduled for lining is adjacent to and under Yackley Avenue and the East Branch of the DuPage River. The Village experienced multiple main breaks last year on this portion of the water main.
OPERATING IMPACT
Operating impacts to the budget to be determined in the future.
PROJECT OBJECTIVES / STATUS
This project will rehabilitate water main located on Burlington Avenue.