EQUIPMENT REPLACEMENT

VILLAGE OF LISLE | FISCAL YEAR 2023/2024 BUDGET

SUMMARY

PROJECT TITLE: Equipment Replacement - 2011 Bobcat S185


DEPARTMENT: Public Works






START DATE (FY): 05/01/2023


END DATE (FY): 04/30/2024

PROJECT DESCRIPTION

This equipment is used for various maintenance activities including pavement patching, parkway grading, water main break operations, and other activities. The new equipment will be upsized from the current model to allow it to be used in tandem with larger hauling vehicles, increasing operational versatility and efficiency.

OPERATING IMPACT

Ongoing operational maintenance of the equipment will continue, but the new equipment with factory warranties will ensure reduced major maintenance costs.

PROJECT OBJECTIVES / STATUS

The unit would be placed in service and improve operational efficiency by allowing the Village to utilize its full compliment of larger hauling vehicles during operations.

PROJECT COSTS

PROJECT FUNDING