Parks, Open Space, Recreational and Cultural Facilities




Parks, Open Space & Recreation

Consultation phase

Former Sunset Golf Course Park Conversion - 2727 Johnson Street

Cost estimate: $12,000,000

Balance to finish: $12,000,000.00

Phase: Phase 1 issuance

Percent Completion: 0%

District: 3


Purchase of the privately owned approximately 45 acre former Sunset Golf Course site for nature preserve and new passive public park space to include nature trails, landscaping, fencing. (Additional grant funding may be needed for park construction based on final approved design).


PROJECT STATUS UPDATE:

Per the City Charter for land purchases, staff is currently securing a certified appraisal on the property through City real estate advisor, CBRE, Inc.



Hollywood Beach Golf Course, Clubhouse, Community Center and Perimeter Park - 1600 Johnson Street

Cost estimate: $12,798,726

Balance to finish: $12,789,723.00

Phase: Phase 1 issuance

Percent Completion: 0%

District: 1


New Clubhouse/Community Center on SW corner to include pro shop, dining area, meeting space, cart barn, staging area, signage and parking. Renovate 18 holes with re-alignment for relocated clubhouse. New irrigation, cart paths, landscaping and course restrooms. New curbing and fencing along 17th Ave.


PROJECT STATUS UPDATE:

Design Consultant Request for Qualifications process completed by staff. On August 28, 2019, the City Commission authorized City officials to negotiate and execute an agreement with the highest ranked firm, McCumber Golf, to provide Architecture/Engineering Design Services.


Orangebrook Golf and Country Club Revitalization - 400 Entrada Drive

Cost estimate: $24,789,613

Balance to finish: $24,789,613.00

Phase: Phase 1 issuance $3,000,000

Phase 2 issuance $21,789,613

Percent Completion: 0%

District: 6


New 15,000 sq ft multi-use clubhouse, ADA accessible nature preserve path within course designed with wildlife habitat/biodiversity for walking, jogging, biking, improved course drainage and water retention capacity, renovate 36 holes of golf to include an 18 hole championship course and an 18 hole Par 3 course, enhance putting/chipping area and driving range, new 10,000 sq ft cart barn, new 12,000 sq ft maintenance building, course restrooms and starter shack, new cart paths, illuminate 9 holes for evening play, parking lot and entryway signage.


PROJECT STATUS UPDATE:


Project status pie graph. Project in planning phase.

Former Armory Building Renovation - 2161 Johnson Street

Cost estimate: $2,411,274

Balance to finish: $5,103,937.00

Phase: Phase 1 issuance

Percent Completion: 0%

District: 2


Renovate building to create an indoor sports facility including basketball/batting cages/soccer goals. ADA compliant restrooms, office space, meeting room, storage area. Exterior landscaping and connect building to Dowdy field.


PROJECT STATUS UPDATE:


Project status pie graph. Project in planning phase.

Dowdy Sports Field - 2161 Johnson Street

Cost estimate: $2,500,0255

Balance to finish: $2,500,255.00

Phase: Phase 1 issuance

Percent Completion: 0%

District: 2


Replace artificial turf field 130 x 100 yds, install new artificial turf field and drainage 130 x 60 yds, re-lamp with LED sports lighting, remove baseball netting, poles, dugout, resurface parking.


PROJECT STATUS UPDATE:


Project status pie graph. Project in planning phase.

Rotary Park - 3150 Taft Street

Cost estimate: $910,0972

Balance to finish: $910,972.00

Phase: Phase 1 issuance

Percent Completion: 0%

District: 3


Add sports field underdrain to Pell, Whitlock, Rotary 1 and Shull fields to imiprove drainage to reduce field downtime. Address run-off from plaza and drainage in alleyway.


PROJECT STATUS UPDATE:


Bicentennial Park - 7300 Farragut Street

Cost estimate: $294,118

Balance to finish: $294,118.00

Phase: Phase 1 issuance

Percent Completion: 0%

District: 5


Replace playground equipment, safety surfacing, shade cover, replace entry fence, replace exercise equipment, resurface walking path and replace ancillary park equipment.


PROJECT STATUS UPDATE:

Purchase order issued, approved by R-2019-175, June 17, 2019, for $229,794.33, the vendor for this project is Kompan Inc. The Purchase Order was issued to the vendor on July 16, 2019.


Project status pie graph. Project in planning phase.

Cathy & Bob Anderson Park - 5800 Thomas Street

Cost estimate: $255,897

Balance to finish: $255,897.00

Phase: Phase 1 issuance

Percent Completion: 0%

District: 4


Replace playground equipment, safety surface, shade system; resurface sport court, walkway and parking lot; and replace ancillary park equipment.


PROJECT STATUS UPDATE:


Project status pie graph. Project in planning phase.

Washington Park - 5199 Pembroke Road

Cost estimate: $286,927

Balance to finish: $286,927.00

Phase: Phase 1 issuance

Percent Completion: 0%

District: 6


Upgrade fields to Bermuda grass, replace field fencing, remodel press box, resurface basketball court, remove baseball field and fence and replace ancillary park equipment.


PROJECT STATUS UPDATE:


Montella Park - 1231 N 69th Way

Cost estimate: $324,019

Balance to finish: $75,360.95

Phase: Phase 1 issuance

Percent Completion: 0%

District: 5


Replace playground equipment, safety surfacing, shade cover and ancillary park equipment.


PROJECT STATUS UPDATE:

Purchase order issued, approved by R-2019-202, July 3, 2019, for $248,658.05. Playground equipment supplier and installing vendor: Rep Services, Inc. The Purchase Order was issued to the vendor on July 31, 2019.


Joe DiMaggio Park - 1001 Three Island Blvd

Cost estimate: $318,199

Balance to finish: $318,199.00

Phase: Phase 1 issuance

Percent Completion: 0%

District: 1


Replace playground equipment, safety surfacing, shade system, exercise pieces and replace ancillary park equipment.


PROJECT STATUS UPDATE:

Purchase order issued, approved by R-2019-201, July 3, 2019, for $260,996.73. Vendor/Installer for this project: Top Line Recreation, Inc.


Project status pie graph. Project in planning phase.

Poinciana Park - 1301 S 21st Avenue

Cost estimate: $261,793

Balance to finish: $261,793.00

Phase: Phase 1 issuance

Percent Completion: 0%

District: 2


Replace playground equipment, safety surfacing, shade cover, resurface basketball court, replace ancillary park equipment and upgrade dog park.


PROJECT STATUS UPDATE:


Project status pie graph. Project in planning phase.

Zinkil Park - 5451 Washington Street

Cost estimate: $604,688

Balance to finish: $604,688.00

Phase: Phase 1 issuance

Percent Completion: 0%

District: 6


Replace playground equipment safety surfacing, shade covers, swing set/turf and replace ancillary park equipment.


PROJECT STATUS UPDATE:


Project status pie graph. Project in planning phase.

Jefferson Park - 1501 Jefferson Street

Cost estimate: $225,966

Balance to finish: $225,966.00

Phase: Phase 1 issuance

Percent Completion: 0%

District: 1


Replace playground equipment, safety surfacing, shade cover and upgrade basketball posts and goals.


PROJECT STATUS UPDATE:


David Park - 108 N 33rd Court

Cost estimate: $159,350

Balance to finish: $11,405.00

Phase: Phase 1 issuance

Percent Completion: 0%

District: 3


Replace playground equipment, safety surfacing, shade system, resurface sport courts and replace ancillary park equipment.


PROJECT STATUS UPDATE:

Purchase order issued, approved by R-2019-200, July 3, 2019, for $147,945.00. Vendor: Bliss Products and Services, Inc.


Project status pie graph. Project in planning phase.

John B. Kooser Park - 1401 Polk Street

Cost estimate: $79,841

Balance to finish: $79,841.00

Phase: Phase 1 issuance

Percent Completion: 0%

District: 1


Replace playground equipment, safety surfacing and ancillary park equipment.


PROJECT STATUS UPDATE:


Project status pie graph. Project in planning phase.

Veterans/Sal Oliveri Park - 4701 Tyler Street

Cost estimate: $149,948

Balance to finish: $149,948.00

Phase: Phase 1 issuance

Percent Completion: 0%

District: 3


Replace playground equipment, replace safety surfacing, shade cover, and ancillary park equipment.


PROJECT STATUS UPDATE:


Project status pie graph. Project in planning phase.

Hollywood West Sports Park - 6770 Garfield Street

Cost estimate: $1,111,320

Balance to finish: $1,111,320.00

Phase: Phase 1 issuance

Percent Completion: 0%

District: 5


Replace artificial turf, replace floratam with bermuda, main field fencing, new bleachers and ancillary park equipment.


PROJECT STATUS UPDATE:


Project status pie graph. Project in planning phase.

John Williams Park -6101 Sheridan Street

Cost estimate: $360,868

Balance to finish: $360,868.00

Phase: Phase 1 issuance

Percent Completion: 0%

District: 5


Replace playground equipment, safety surfacing, shade system, resurface walking path and ancillary park equipment.


PROJECT STATUS UPDATE:


Project status pie graph. Project in planning phase.

Holland Park/Sailors Point - 801 Johnson Street

Cost estimate: $697,619

Balance to finish: $697,619.00

Phase: Phase 1 issuance

Percent Completion: 0%

District: 1


Refurbish pavilions and restrooms, resurface parking lot, replace floating docks, install shade system, refurbish observation tower.


PROJECT STATUS UPDATE:


Cultural Facilities

Art and Culture Center Multidisciplinary Arts Education Center - 1650 Harrison Street

Cost estimate: $2,500,000

Balance to finish: $2,500,000.00

Phase: Phase 1 issuance

Percent Completion: 0%

District: 1


City contribution to construction of multidisciplinary arts-education spaces and expansion/renovation of existing visual arts galleries. Multipurpose dance/drama room, visual arts and music classrooms, distance learning broadcast studio, mixed-use studio theater, interactive contemporary gallery and meeting/reception room.


PROJECT STATUS UPDATE:

Grant application for $500,000 submitted to State of Florida Cultural Arts Commission in June 2019. Presentation to state scheduled in October, 2019. Professional Architectural and Engineering Services for design awarded to Brooks & Scarpa Architects, Inc. on September 18, 2019 in the amount not to exceed $250,000.

ArtsPark at Young Circle

Project status pie graph. Project in planning phase.

ArtsPark at Young Circle - 1 Young Circle

Cost estimate: $496,019

Balance to finish: $496,019.00

Phase: Phase 1 issuance

Percent Completion: 0%

District: 1


Install decorative fence/wall around amphitheater to allow for ticked events. Replace playground pieces and safety surfaces.


PROJECT STATUS UPDATE: