The Escambia County Budget

This is your window into Escambia County's budget and finances. Use the tools below to learn about the County's unique budget process, view our most frequently asked questions, and explore all of the County's financial information - online, anytime.

Waste Services

Waste Services Header Photo

Mission Statement

Provides efficient, responsive services that enhance the quality of life, meet common needs, and promote a safe and healthy community.

Objectives / Priorities

  • Inform/educate employees regarding landfill compliance/maintain professional services contracting
  • Focus on staff recruitment, training and retention
  • Rehabilitate existing heavy equipment for daily operations
  • Drive efficient landfill gas collection and evaluate use for increased volume
  • Focus on Leachate treatment and disposal alternatives
  • Evaluate waste diversion strategies
  • Increase community involvement and neighborhood cleanups

Goals

  • Maintain all Waste Services facilities in full compliance with Federal, State and Local regulations
  • Establish staffing at optimum levels
  • Continue efficient compaction of waste material
  • Manage and improve Gas Collection System
  • Ensure ongoing waste disposal capacity through compaction efficiency and future expansion
  • Partner with interlocal agencies to increase leachate discharge capacity
  • Minimize necessary closure of PTS due to excess tipping floor waste

Performance Measures

 

FY 2022/2023

Actual

FY 2023/2024

Actual

FY 2024/2025

Estimate

FY 2025/2026

Estimate

100% Complete of Additional Waste Disposal Capacity 100% 100% 100% 100%
100% Ops Staff Trained in Accordance with FAC 62-701 100% 100% 100% 100%
12-Month Average of 1200 scfm Gas Generation to Renewable Energy Plant 1,200 1,200 1,200 1,200

Benchmarking

  Escambia County Target
Landfill Gas to Electrical Generation 1,200 scfm 1,250 scfm
Waste Compaction Density 1,600 lbs/cy 1,600 lbs/cy

Funding Priorities

Major Issues Funded Amount
Continuation of Landfill Expansion Permit and Design $1,200,000
Tipping Floor Conversion to Equipment Maintenance Shop (PLF) $750,000
Alternative Leachate Management $700,000
Rebuild/Replacement of Aging Heavy Equipment $1,600,000
Achieve 100% Staffing Level $443,000
Beulah Rd Relocation Design $1,000,000
Replace Landfill Flare

$1,200,000

Install New Gas Collection System (Section V Cell IB) $450,000

Significant Changes for Fiscal Year 2025 / 2026

  • Assess internal reclamation of airspace
  • Continue design and permitting process for Landfill expansion project