Public Works – Streets Division
Project #0316
Reconstruct 1st St (4th Ave to 650blk)
1st Street from 4th Ave to 650 block (~1050lf)
Project Information/Description
Contract to remove existing full depth pavement section and repair subbase, where needed, replace subgrade and full depth asphalt pavement. This is a replacement of AC pavement which has reached the end of its useful life.
Project Details
Estimated at $55.00/ SY; Total Estimated = $257,000 = $300,000 w 115%
Prioritization Criteria

Project by Fund
Project Timeline
Estimated Completion: December 2023