Public Works – Streets Division

Project #0313

Reconstruct Junction St (W2nd to W 28th)

Junction Street from W 2nd Ave to W 28th St. (~2000lf)

Project Information/Description

Contract to remove existing full depth pavement section and repair subbase, where needed, replace subgrade and full depth asphalt pavement. This is a replacement of AC pavement which has reached the end of its useful life.

Project Details

Estimated at $55.00/ SY; Total Estimated = $453,000 = $520,000 w 115%

Prioritization Criteria

Project by Fund

Project Timeline

Estimated Completion: December 2023

Funding Strategy