Public Works – Streets Division
Project #0314
Reconstruct Red Mountain (End to End)
Red Mountain from end to end (~1300lf)
Project Information/Description
Repave intersection and associated roadways
8th Ave from College St to 2nd St and
College St from 8th Ave to 2nd AveUpon completion of roadwayrealignment and concrete work to intersection by MultiModal
Project Details
Estimated at $55.00/ SY; Total Estimated = $318,000 = $366,000 w 115%
Prioritization Criteria

Project by Fund
Project Timeline
Estimated Completion: December 2023