CAPITAL IMPROVEMENT PROGRAM (CIP)

Project # FP20500

PROJECT DETAILS AND PRIORITY

Project: DBC Slope Stabilization (Construction)


Phase: Construction


Status: New


Priority: 1 - Mandatory: Must Have


FY 22/23 Budget: $1,260,000

PROJECT DESCRIPTION

The project will address the potential footing and slab settlement along the north/northwest perimeter of the Diamond Bar Center building.

TIMELINE

Project Start: July 2022


Construction Start: November 2022


Completion: June 2023