CAPITAL IMPROVEMENT PROGRAM (CIP)

Project # SI23104

PROJECT DETAILS AND PRIORITY

Project: CDBG Area 3 ADA Curb Ramp Project (Const.)


Phase: Construction


Status: New


Priority: 1 - Mandatory: Must Have


FY 22/23 Budget: $184,000

PROJECT DESCRIPTION

The project includes upgrading existing curb ramps and installing new curb ramps that meet the latest Federal ADA Compliance Standards.


Area 3 is located east of the western City limits, north of the southern City limits, south of Pathfinder Rd, and west of the Country Estates.

TIMELINE

Start: August 2022


Construction Start: March 2023


Completion: May 2023