City of Diamond Bar Budget

Fiscal Year 22/23


CAPITAL IMPROVEMENT PROGRAM (CIP)

Project # TM22200

PROJECT DETAILS AND PRIORITY

Project: Battery Back-Up and CCTV Replacement Program


Phase: Construction


Status: Ongoing - With New Request


Priority: 1 - Mandatory: Must Have


FY 22/23 Budget: $61,000

PROJECT DESCRIPTION

The Battery Back Up and CCTV project will replaced existing aging equipment that was originally installed in 2008 to 2011.


Replacement Locations:

- Golden Springs Drive/Lemon Avenue

- Diamond Bar Blvd./Pathfinder Road

- Diamond Bar Blvd./Brea Canyon Road


TIMELINE

Start: July 2022


Completion: December 2022