City of Diamond Bar Budget

Fiscal Year 22/23


CAPITAL IMPROVEMENT PROGRAM (CIP)

Project # SI23101

PROJECT DETAILS AND PRIORITY

Project: Residential and Collector Street Rehab.- Area 3, 4, 5 (Design)

Arterial Street Rehab - 3 Locations (Design) [Locations Pending PMS Update]

CDBG Curb Ramp - Area 3, 4, 5 (Design)


Phase: Design


Status: New


Priority: 1 - Mandatory: Must Have


FY 22/23 Budget: $380,000

PROJECT DESCRIPTION

The project includes the design of street improvement plans for residential and arterial street rehabilitation program for the next three years. The locations are prioritized using the City's latest Pavement Management Plan.


Areas 3 and 4 are located east of the western City limits, north of the southern City limits, south of the northern City limits and Pathfinder Rd, west of the Country Estates, and west of the 57 freeway. Area 5 is located towards the north of the City between the 60 freeway, Diamond Bar Blvd, and the neighbourhood north of Pantera Park. The arterial roadway limits will be determined by the pavement management plan.

TIMELINE

Start: September 2022


Completion: June 2023