City of Diamond Bar Budget

Fiscal Year 22/23


CAPITAL IMPROVEMENT PROGRAM (CIP)

Project # SI23102

PROJECT DETAILS AND PRIORITY

Project: Residential and Collector Street Rehab - Area 2 (Const.)


Phase: Construction


Status: New


Priority: 2 - Needed: If Delayed Will Cost More to Fix


FY 22/23 Budget: $2,600,000

PROJECT DESCRIPTION

The project includes the application of slurry seal over the existing pavement and AC edge grind and overlay. This type of maintenance activity is performed annually throughout the City on residential streets to extend the life of the roadways.


Area 2 is located west of Diamond Bar Blvd, east of the 57 freeway, south Grand Ave and north Pathfinder Rd.

TIMELINE

Start: May 2023


Completion: August 2023