City of Diamond Bar Budget

Fiscal Year 22/23


CAPITAL IMPROVEMENT PROGRAM (CIP)

Project # PW23401

PROJECT DETAILS AND PRIORITY

Project: Groundwater Drainage Improvements-Phase 4 & 5 (Copley & Moonlake)


Phase: Design & Construction


Status: New


Priority: 2 - Needed: If Delayed Will Cost More to Fix


FY 22/23 Budget: $130,000 (Design)

$530,000 (Construction)

PROJECT DESCRIPTION

The project includes the design and construction of drainage devices to divert groundwater that continuously flows through Copley Drive from the hillside behind City Hall as identified on the Citywide Comprehensive Drainage Study completed in 2015.

TIMELINE

DESIGN


Start: September 2022


Completion: January 2023


CONSTRUCTION


Start: February 2023


´╗┐Completion: April 2023