Capital Improvement Plan
FY 2021-22 Budget
The Capital Improvement Plan (CIP) is a planning document that covers the construction and maintenance of major projects and facilities as well as major studies. The CIP also serves as a budget that provides the means to pay for these projects.
This section includes the Town's Five-Year Capital Improvement Plan for FY 2021-22 through FY 2026-27.
CIP Project Categories
Colma’s Capital Improvement Plan (CIP) lists projects in four distinct categories, below. Click on the images below to get to the project description, FY 2020-21 status, FY 2021-22 work plan, and funding needs for FY 2021-22 through FY 2026-27.
Project Status
The project status is shown on each capital project. The statuses are Active, Closed, Future or Unfunded.
- Active - existing or new CIP projects that have available funding and activities (spending) in FY 2021-22.
- Closed - CIP projects that have been completed or have been closed out. These projects will only appear in future CIP budgets if they have project expenditures during the prior three years.
- Future - CIP projects that are programmed for FY 2022-23 through FY 2026-27. Project budget and funding are identified, but are not earmarked.
- Unfunded - CIP projects that are Town priorities but are currently without budgeted funds. Unfunded projects will be reviewed annually during the Town Budget process to see if funds are available for construction and if the proposed projects are ready to move from the Unfunded to the Budgeted projects list.
This will provide more clarity in the Capital Improvement Budget. It will also identify projects that are budgeted, projects that are ready to be closed (and dropped from future CIP budgets) and future projects that are currently unfunded today but are in the developmental stage awaiting conceptual design approval, plans and specifications, and additional funding from the Town and/or outside sources.
FY 2020-21 Capital Improvement Program Overview
During to the Covid 19 pandemic, the Town focused on projects that met the Town's Covid 19 pandemic goals. These goals include ensuring public safety, preserving reserves, and utilizing all available grant funding. FY 2019-20 Active Projects that met these goals were El Camion Real Bicycle & Pedestrian Plan (914), Mission Road Bicycle & Pedestrian Improvement (903), General Plan Update (991) and Climate Action Plan (994). The Town continued to fund the IT Infrastructure Upgrades (986) as online and virtual office support increased during the Covid 19 pandemic. By March 10, 2021, the City Council approved the addition of three capital programs:
- F-Street Retaining Wall (902) - ensuring public safety
- Housing Element Update (996) - utilizing grant funding
- Zoning Code Update (997) - subset of General Plan Update (991)
Of all the projects listed above, Climate Action Plan (994) and El Camino Real Bicycle & Pedestrian Plan (914) are completed and will close as of June 30, 2021. All other projects will continue into FY 2021-22, with the IT Infrastructure Upgrades (986) continuing as an ongoing program. The projected total carryover, as of April 30, 2021, is $235,000, with $80,000 programmed for FY 2022-23. Actual carryover will depend on actual project spending through June 30, 2021 and will be part of the year-end process.
FY 2021-22 Capital Improvement Plan Highlight
In addition to the six projects listed above that will continue into FY 2021-22, the Town has added five additional projects, continues two ongoing projects, and re-establishes one deferred project.
Additional Projects:
- Annual Roadway Rehabilitation and Preventative Maintenance (906) - $150,000
- Colma Museum Facility Repair and Painting (951) - $75,000
- Facility Parking Lot Upgrades (953) - $99,025
- Financial Software Replacement (965) - $100,000
- Police Body Worn and In-Car Cameras [part of the Equipment Purchase and Replacement Project (984)] - $201,000
Ongoing Projects:
- IT Infrastructure Upgrades (986) - $50,000
- Vehicle Replacement (987) - $164,000
Deferred Projects:
- Creekside Villas Repair (952) - $40,000 - included in the carryover budget discussed above.
Project Funding and Spending Plan for FY 2021-22 through FY 2026-27
The Funding Plan table below summarizes the revenue sources that the Town plans to use to support the capital program. The funding identification process includes apply grant and special fundings first to the capital project, then special contributions, and finally the General Fund or the Capital Reserve Fund.
The Capital Program bar chart below summarizes the projects by categories. The corresponding table is below the bar chart. To get to the table, use the scroll bar on the right of the bar chart. At first glance, the table shows the total program by fiscal year and by categories. The project list is also available in the table by clicking on the triangles on the left of the categories.

Reasonable Accommodation
Upon request, this publication will be made available in appropriate alternative formats to persons with disabilities, as required by the Americans with Disabilities Act of 1990. Any person with a disability, who requires a modification or accommodation to view the document, should direct such a request to Pak Lin, Administrative Services Director, at 650-997-8300 or pak.lin@colma.ca.gov Please allow two business days for your request to be processed.