Burnley-Moran Elementary school Roof Replacement

FISCAL YEAR 2024 BUDGET

SUMMARY

Project Name: Burnley-Moran Roof Replacement

Department: Public Works Department

Start Date: 6/30/2026

End Date: 8/30/2027

PROJECT DESCRIPTION:

This funding will provide for the needed roof replacement at Burnley-Moran Elementary School.

RELATIONSHIP TO comprehensive PLAN:

Chapter 9 : Community Facilities and Services


Goal 1. Efficient Planning for Facilities and Infrastructure

Prioritize efficient construction and maintenance of all community infrastructure and facilities, and ensure that infrastructure capacity is built and maintained in line with growth or declining demand, as appropriate.


Goal 2. City Schools

Improve and maintain public school facilities to continue providing an excellent education to students.

PROJECT OBJECTIVES / STATUS:

Objectives: To replace the Burnley-Moran roof, which will begin to fail if not replaced on schedule with a new solar-ready roof.


Status: We are in the initial scoping phase.

Cost Estimate

Operating Impacts

Operating impacts to be determined in the future.