Wastewater System - Pump Station 4 Upgrade

2023-2028 CFP

Pump Station 4 Upgrade

SUMMARY

PROJECT TITLE: Pump Station 4 Upgrade

DEPARTMENT: Wastewater

BUDGET CODE: 440-760-594.35-62-CFP-SEW-00017

JUSTIFICATION: Improves existing service

START DATE (FY): TBD

END DATE (FY): TBD

PROJECT DESCRIPTION:

Upgrade Pump Station 4 to include a larger wet well and pumps, flow monitoring and upgrade electrical and emergency power to support new pumps.

RELATIONSHIP TO STRATEGIC PLAN:


PROJECT OBJECTIVES / STATUS:

With consideration to the Padilla Heights and Reservation Road sewer extension projects. Pump Station 4, which all of the sewer flow from the March Point area, will need a larger wet well and new pumps to increased capacity to accommodate the added flow.

Cost Estimate

Funding Sources

Operating Impacts

Operating impacts to be determined in the future.