Water System - Regional: Construct Storage Building

2023-2028 CFP

SUMMARY

PROJECT TITLE: Water System - Regional: Construct Storage Building

DEPARTMENT: Public Works

BUDGET CODE: CFP-WTR-00013

JUSTIFICATION: Improves reliability of service

START DATE (FY): TBD

END DATE (FY): TBD

PROJECT DESCRIPTION:

Construct a new storage and maintenance shop building at the water treatment plant.

REcommendation:

Currently, equipment and spare parts are scattered throughout the water treatment plant. A centralized storage facility will allow for a more efficient operation of the plant as well as additional space for a larger inventory of spare parts. This facility will provide workspace to make repairs on aging equipment.

PROJECT OBJECTIVES / STATUS:

No change: extension of planned project.

Cost Estimate

Funding Sources

Operating Impacts

Operating impacts to be determined in the future.