Wastewater System - New Wastewater Treatment Plant Outfall

2023-2028 CFP

WWTP Outfall

SUMMARY

PROJECT TITLE: New Wastewater Treatment Plant Outfall

DEPARTMENT: Wastewater

BUDGET CODE: 440-750-594.35-63-CFP-SEW-00015

JUSTIFICATION: Replace Old Outfall, Increase Capacity

START DATE (FY): TBD

END DATE (FY): TBD

PROJECT DESCRIPTION:

Relocate and replace existing outfall with a larger outfall that can handle increasing flow from the Wastewater Treatment Plant for the next 50 to 100 years.

RELATIONSHIP TO STRATEGIC PLAN:

Replace existing Outfall

PROJECT OBJECTIVES / STATUS:

Relocate and replace existing outfall

Cost Estimate

Funding Sources

Operating Impacts

Operating impacts to be determined in the future.